Perform Activity
Explanation
The work that has been planned on an activity can be performed as actions that are continued in other product
areas of IFS Cloud and as actions in real life operations.
While some of the processes in these product areas use IFS/Project Management as a starting point, others use it
as a follow through in the process flow. Processing of a customer order or purchase order in the application is an
example of how IFS/Project Management collaborates with processes in other product areas. A few are listed
below:
- Material Requirements Planning and Project Material Requirements Planning
- Master Scheduling
- Project Inventory
- Procurement
- Customer Order
- Shop Order
- Work Order
- Project Reporting
Refer the Project Management process description for further information regarding these processes.
Actual work such as building a wall, painting the house, manufacturing or buying a part etc., for which the
progress can be reported on the object being executed (such as a shop orders, work orders, tasks etc.), or be
reported manually direct to the activity. When objects connected to an activity are executed and project
transactions are created, cost, hours, revenue and progress information will be retrieved and displayed per
cost/revenue element for the activity.
- Cost and hour values are retrieved from the objects to the activity as described in About Cost, Hours
and Revenue Reported to Activity for cost reporting objects.
- Revenue values are retrieved from the objects to the activity as described in About Cost, Hours and
Revenue Reported to Activity for revenue reporting objects.
- Earned Value and progress values are retrieved from the objects to the activity as described in About
Earned Value and Progress for applicable objects. The values reported are dependent on the
Planned Cost Driver, Progress Method and Earned Value Method
selected for the activity and project.
Prerequisites
- The activity should be released.
System Effects
- The Planned, Planned Committed, Committed, Used and Actual field values in
the Cost and Hours tabs are updated for the for the selected activity, based on the connected
objects and their statuses etc.
- The Planned, Preliminary, Posted and Actual field values in the Revenue
tab are updated for the selected activity, based on the connected objects and their statuses etc.
- Object information, such as progress and status, is updated and displayed in the Project Connections page and
Activity Monitoring - Project Connections page .
- The Reported Hours and Reported Cost fields in the Planning tab of
Project Resource Planning and the Activity Resource Planning pages are updated when work has been
performed and time is reported by an employee who belongs to a resource group.
- The Calculated Cost Progress and Calculated Hours Progress field values on the activity level
are updated according to the selected Progress Method. The Weighted Average Development values on sub
project and project level are also updated.