Set Resource Relocation to Active
Explanation
This activity relates to the actions required to update a Resource Relocation to an Active status. Only
Relocations of a Preliminary status can be updated, once updated to a status of Active the Capacity and Shift
Generation background job will trigger to update the resource's capacity and shift information.
Prerequisites
A Resource Relocation exists in a Preliminary status.
System Effects
- The Resource Relocation is changed and updated to a status of Active.
- If the Resource Basic Data setting: Auto Trigger Shift Generation Upon
Status Change is enabled then following a status update to Active the Shift and Capacity Generation will
trigger automatically to update the resource shift information.