Report In Work Task
Explanation
This activity is used to report the work task upon its completion. It is used by both, the Coordinators and
Executors, to report the Performed Work, Time and Tools. It also facilitates to Issue and Return materials when
completing the work task.
The contact information of the person who has reported the work can be seen in the Work
Task page of both, the Executor and Coordinator in Contact and Reporter
Information.
Prerequisites
- B2B interface, Coordinate Work or Execute
Work must be available and accessible, respective to the user being the Coordinator or the
Executor.
- Log in user must have the respective B2B Supplier - User connection.
- Work Task must be coordinated by the logged in User.
- Work Task must be in status Work Started.
- Work Task must have either no assignments or all completed assignments.
System Effects
- Work Task is set as Work Done.
- Time and Tools are reported.
- Materials are issued and Returns are registered.