Modify Time to Complete
Explanation
Use this activity to update the hours required for remaining work during the Multiple Visit Handling.
This activity is typically used:
- During the execution of work assignments in visit chain or,
- When completing a work assignment of a visit chain, which does not have follow-on visits.
- When Incomplete a work assignment.
Prerequisites
- Visit chain must exist
- Work Assignment is not Completed or Incompleted or Canceled
System Effects
- In the background it updates the total work duration of the corresponding activity.
- Need Readjustment symbol is displayed on visits in Resource Monitoring Gantt
- If IFS/Planning and Scheduling Optimization is used, then the visit chain is updated accordingly.