Clock Out after work is done
Explanation
This activity is used to clock out of a work assignment. When the Clock In/Clock Out feature is used, time
reporting is done automatically.
When you clock out, the effective hours between clock in and clock out will be calculated and a work task
transaction will be created for the time spent.
Prerequisites
- A work task should have been defined with a work assignment.
- The work task must be in released status or higher.
System Effects
- When Clock Out option is selected on a work assignment, the existing clocking record will be updated with in
Work Task Clockings page with the date and time you clocked out updated as Stop Time.
- The time taken for the work is automatically reported. i.e., a cost line and the relevant work task
transaction is created.
- When Clock Out on the Crew Clock In, A Transaction will be created without Accounting information
(Transaction Type = "Collective"). A Work Task Transaction for each crew member will also be created
with appropriate accounting information.