Define Tool/Equipment Demands
Explanation
This activity is used to define tool/equipment resources required to perform a specific work task on Work
Task/Resources tab Demands section, including the duration for which they are planned. One
or more Tool/equipment demands can be stated on a task. These demands can either be defined only with a
Resource Group or as Resource along with the Resource Group.
A Sales part site and Sales part can be added on the demand line if the price needs to be invoiced
to the customer.
Prerequisites
- Resources and Resource Groups need to be defined and connected to each other in Resource Navigator and have
connections for the work task site.
- Resources and Resource Groups should be compatible to use in Maintenance.
System Effects
As a result of this activity,
- Demand lines with Demand type Tool/Equipment will be connected to the task.
- The Planned Hours field for the resource demand will default to the work task's duration
but can be adjusted as needed. The specified resource duration will be reflected in the planned resource
costs.
- Resource activities will be generated for demands based on the planned hours specified for each resource.