Postpone Latest Finish
Explanation
This activity is used to postpone the Latest Finish date already set on the work task due to a certain condition
and to record that reason. e.g. labor shortage or lack of material.
Prerequisites
Following conditions must be met to keep track and enter a postponement reason:
- The Work Task must exist in the Prepared, Released, Work Started,
Work Done or Reported status.
- The Latest Finish Date on the work task is already entered.
- The Work Type set on the work task must be enabled to enter postponement reason in Work Type
Basic data.
System Effects
As a result of this activity,
- Work Task Original Latest Finish date will retain the first Latest Finish date, even if
postponed multiple times.
- A dialog will appear to enter the Reason and it is mandatory. After saving it will be
displayed in the Work Task
- In the Work Task/Additional Information, Postponed check box will be set to
Yes.
- An Event Log is created for this event. Event Logs are generated in the Events tab
found in the Attachment panel of the Prepare Work Order page.