Click the Publish Work Package button to transfer the assigned tasks and faults to the maintenance
execution.
Confirm that the equipment baseline is aligned with the target maintenance execution solution (e.g., Line
Maintenance, Hangar Maintenance). This alignment enables accurate transmission of data such as tools, parts, and
measurements within the Work Package.
Work package must have been created.
Equipment Baseline should be aligned with the target execution solution.
The work package will be published to the execution.