A Change Order (CO) is used in engineering to register, plan, and manage formally approved changes to products,
components, or technical documentation. The CO process ensures that all changes are evaluated, tracked, and
implemented in a controlled and documented manner, supporting quality and traceability throughout the engineering
lifecycle.
The purposes of the Change Order (CO) are as follows:
Register and maintain information on approved
engineering changes.
Plan the implementation of changes, including
scheduling and resource allocation.
Manage ongoing changes with a focus on execution,
progress, and cost control.
Analyze completed changes to support continuous
improvement and reduce future errors.
Document and track changes to specific objects, parts,
or assemblies.
Change Order Statuses
Preliminary – The CO is being
prepared. Information is collected and initial analysis is underway. This is the default status for new change
orders.
Analyzed – The impact, cost, and
feasibility of the change have been reviewed. The CO is ready for evaluation and further action.
Approved – The CO has been
reviewed and approved for execution. No additional Change Requests (CRs) can be connected after this point. When
set to Approved, all connected CRs are automatically set to Processed.
Performed – The change has been
executed according to the plan.
Completed – All actions related
to the CO are finalized, and the change is fully implemented. The status can be changed back to Performed if the
CO is reopened.
Canceled – The CO will not be
started or completed, and cannot be connected to a CR. Cancellation can occur at any time if the CO cannot
proceed to the next status.