Update Resource Capacity
Explanation
This activity is used to update the resource capacity when unplanned work tasks result from limitations in
available resource capacity.
If resources capacity appears inadequate, it is important to review the following:
- Used in Maintenance must be Yes for all the resource groups from which
resources are used.
- Individually planned person resources must be connected to the relevant Maintenance
Organization(s)
- Make sure all individually planned resources have their resource schedules generated. This can be viewed in
the Resource Availability page. If the schedule is not available, generate the schedule.
- Make sure all resource groups planned on group level (capacity calculation base =
Group ) have the planned site(s) connected and also have a generated calendar
connected.
Prerequisites
- Maintenance Planning and Scheduling Dataset has been enabled and sent to IFS Planning &
Scheduling Optimization (PSO) engine and schedule returned by PSO has been saved in IFS Cloud. Analyzing the plan
result found some discrepancies.
System Effects