Update Labour Requirements
Explanation
Use this activity to add, change, or remove the labour requirements on a non-routine's task, so that the
planned skill, hours, certification, and independent inspection match the work to be done.
The labour requirements are held on the Labor list on the Task Execution tab
of the Open and Deferred Fault page. The same list is available on the Open
Task page.
For each requirement you set the Skill and the Work Performed Sched. Hours,
and specify whether certification and independent inspection are required, together with their scheduled hours. The
Stage, and the technician, certifier, and inspector who perform the work, are shown for reference.
Removing a requirement is recorded with a note.
Prerequisites
- An open non-routine or task exists, with the Task Execution tab available.
- The task is not batch completed.
- The non-routine is not assigned to a work package that is In Work.
Procedure
Add a labour requirement
- Open the Open and Deferred Fault page (or the Open Task
page) and open the Task Execution tab.
- In the Labor list, select New.
- Select the Skill and enter the Work Performed Sched. Hours.
- Set Certification Required and, if required, enter the Certification Sched.
Hours.
- Set Independent Inspection Required and, if required, enter the Independent
Inspection Sched. Hours.
- Select Save.
Edit a labour requirement
- In the Labor list, edit the row and change the hours or the certification and inspection
flags.
- Select Save.
Remove a labour requirement
- In the Labor list, delete the row.
- In Remove Labor Requirement: Notes, enter a Note.
- Confirm the removal.
System Effects
- A new labour requirement is created with the Stage set to ACTV.
- Edited hours, certification, and inspection values are updated on the requirement.
- A removed requirement is deleted from the Labor list, and the note is recorded.