Perform Selective MRP
Explanation
Use this activity to run MRP for selected set of part(s) or desired low levels.
Prerequisites
- BOMs must have been defined for the parts, and lead times for both the purchased and manufactured parts must
have been established. MRP only uses the existing product structure with the alternate " * "
indicated by an asterisk(*).
- You can execute selective MRP for sales part in customer order line, part for which the MRP action messsage
is raised in previous MRP run or MS Level 1 part directly. In order to do that customer order line, MRP action
message or MS Level 1 part should be available.
- To perform MRP for master scheduled parts you must first have created a master production schedule using
IFS/Master Scheduling.
- To perform MRP for project planned parts you should first run PMRP.
Note: MRP does not process parts with planning methods B - Order Point Planning, C - Replenishment Level,
M - Manufacturing Cell Part or N - Next Level Demand. Selective MRP is not available in project MRP. Selective
MRP plan part(s) in single site.
System Effects
- Selective MRP will be performed and supplies will be planned for the inventory part(s) and their
components.
- When both IFS/Material Planning Simulation and IFS/Project Material Requirements Planning are installed, the
Prepare PMRP Simulation Profile Data background job is posted after each live site,
planning network, or selective MRP run in Material Planning Scenario 1. The job captures a snapshot of the
nettable standard inventory by inventory location. This captured inventory data is used by PMRP simulations that
use Simulation Profile as the Simulation Source.