You create discard requirements for LLPs to make sure they are
discarded upon expiration. After the component has been destroyed (rendered permanently
unrepairable), a certificate of destruction is issued for the LLP, after which its status is
set to SCRAP in Maintenix.
To create a requirement to discard LLPs, do the following:
- On the Requirement Search
page, click Create Requirement.
- On the Create Requirement page, provide the required
information. Note the following:
- Click OK
You must now add a scheduling rule to this
requirement.
- On the details page for the requirement, click the
Scheduling tab.
- Click Add Scheduling Rule
.
- On the Add Scheduling Rule page,
provide the required information. Note the following:
- Usage Parm: Select
CYCLES (Cycles) or HOURS (Flying
Hours).
- Threshold: Enter the
value for life limit of the part. For example, if the LLP is set to expire
after 15000 cycles, enter 15000.
- Deviation (Qty): Enter
0.
- Sched to Plan Low: Enter
0.
- Sched to Plan High: Enter
0.
- Click OK.
Note: A discard requirement is not used to remove the inventory
item from an assembly, therefore a replacement requirement must also be
defined against the configuration slot. This replacement requirement will
then be automatically created by Maintenix to uninstall the LLP component, so that the
discard requirement can be completed.