Package and complete tasks done in the past
You can package one or more tasks that were completed in the past on an inventory item, and record their completion date in a single operation. Since packaging and completing in one step does not let you record details in individual tasks, it is best to use this feature to record the completion of simple tasks.
- The aircraft has missing components or overdue tasks; in these cases, the packaged tasks are completed but the work package remains in work.
- One or more of the selected tasks contains a part request with an invalid inventory serial number in these cases, the affected tasks remain active and the work package remains in work.
Note that, if at the time the work was completed, a tracked component was installed on the aircraft but it has since been removed, the work package that is created automatically shows the component that is currently installed, not the one that was installed at the completion date.
The package and complete options are also available on the corrective task pages of faults.
- The selected tasks are completed and are no longer shown in the Open Tasks tab.
- The work package that was automatically created is also completed, unless there are conditions that prevent the completion as outlined above.
- If you chose the Package and Complete and Enter Usage option, the following comment appears in the usage snapshot area of the completed work package: "These values were manually entered", indicating that Maintenix will not be auto-adjusting these values in the future.
- On the Inventory Details page, Historical tab, Usage sub-tab, a usage record is created for any removed or installed components.