Set Work Assignment Status to Incomplete
Explanation
Use this activity when you cannot complete the planned work fully during the current assignment. When setting a
Work Assignment to Incomplete, an Incomplete Cause must be provided.
If you select an Incomplete Cause with Do not reassign to me flag enabled,
this Work Task will not be rescheduled to the same resource that set the Work Assignment to Incomplete. If a
Scheduling Solution is used, this action also creates a Resource Preference with Preference 0, on the Work Task in
Work Task\Scheduling Information.
It is possible to specify how much time remains to complete the remaining work at the same time, and the
Time to Completion attribute on the Work Assignment is updated accordingly in the back office.
If creating follow-on work to complete the remaining work is enabled for the Work Task through a Workflow Configuration, the you will be presented
with the following options:
- Assign to me : This opens the next step for the assistant to create a new Work Assignment
for the same resource. The new assignment is available for you on mobile.
Note : This option is not valid if you select an Incomplete Cause which has
Do not reassign to me flag enabled.
- Needs to be planned : This opens the next step for the assistant to create a new resource
demand for the Work Task. It is possible to specify a preferred resource for this resource demand as well.
For more information, read about the general behavior on the incomplete state event in Set Work Assignment to Incomplete.
Prerequisites
- A work assignment should exist.
- If there is any work performed through the work assignment, the usages should be reported in.
- Incomplete codes must be defined in Incomplete Cause page.
- To allow the technician to create follow-on work for the remaining work , this should be enabled through a
Workflow Configuration with Configuration Type - Work Task or
Configured Work Task. The relevant configuration should be applied to the Work Task,
and the action Restrict Follow-on Work Actions On Incompletion must be disabled.
System Effects
- The Work assignment will be set to status Incomplete.
- The Assignment Finish Date on the work assignment is updated with the current date.
- If the work assignment is in status Work Started, the Work Finish Date is
updated with current date.
- If the user selects an Incomplete Cause with Do not reassign to me flag
enabled, Scheduling preference for this resource will be updated to 0 on the Work Task. It will also be visible
for dispatchers against the Work Assignment that was set to incomplete in IFS Cloud.
- If follow on work assignments exist (visits), those will be cancelled.
- If creating follow-on work is enabled for the Work Task, the follow-on work will be created as below :
- If the user selects the option Assign to me , a new resource demand and an assignment
for the demand is created for the Work Task. The new assignment will be available in My
Work list.
- If the user selects the option Needs to be planned and proceeded to create a new
resource demand, a new resource demand will be created for the Work Task and will be available for
dispatchers for planning.