Create Structure from Interim Order
Explanation
This activity is used to create a DOP structure as a copy of an interim order structure.
To create a DOP structure from an interim order structure from the DOP Header page,
click Create Structure and then Create Structure.
Prerequisites
- An interim order structure must have been created for the customer order line pegged to the DOP header.
System Effects
- DOP orders are created with quantities and in a structure similar to the interim order structure.
- The status of the DOP orders will be Unreleased unless Auto Release has been enabled in the
Settings section on the Details tab on the DOP
Header page. In that case, the status will be Released. Releasing a DOP order means
generating a shop order or a purchase requisition for the DOP order.
- When releasing pegged project specific DOP orders, the system will generate project specific shop orders
or purchase requisitions/purchase orders dependent on the part type. These orders will be received into the
project inventory.
- A valid routing revision and buildable routing alternate will be added for each DOP order. If no buildable or
plannable routing alternate exists for the part a DOP log is created, but the creation of the structure will
continue. If the routing is serial effective and no serial numbers are reserved for the DOP order a DOP log is
created, but the creation of the structure will continue.
- The due dates and start dates are set for each DOP order in the structure. For information on how this is
done, see Plan DOP Orders.
- If the site has Schedule and Create Load for DOP Order Operations enabled, machine and labor
load of source Scheduled DOP are created for the DOP order operations based on the quantity
remaining to supply on the DOP orders, plus the planned supply scrap for that quantity. This applies to the DOP
orders with manufactured parts that have the status Unreleased and Create
Pegged set to Pegged Orders.