Plan DOP Order
Explanation
This activity is used to plan a DOP order that has been manually created by changing the status of it from
Created to Unreleased. This is required in order to create a structure for the
DOP order, for example by adding a branch or to release the order.
To plan a DOP order, click Plan. You can also click Status and then
Plan on the Components tab of the parent DOP order.
Prerequisites
- A DOP order with the status Created exists.
System Effects
As a result of this activity:
- The status is changed to Unreleased.
- The start date is updated for the DOP order. For information on how this is done, see Plan DOP Orders.
- If the site has Schedule and Create Load for DOP Order Operations enabled, machine and labor
load of source Scheduled DOP are created for the DOP order operations based on the quantity
remaining to supply on the DOP order, plus the planned supply scrap for that quantity. This applies if the DOP
order is for a manufactured part and has Create Pegged set to Pegged
Orders.