Propagate Date Upstream
Explanation
This activity is used to propagate dates upstream in a DOP structure (to child levels of the structure). The
dates at child levels in the DOP structure will be adjusted based on the due date of the DOP order from which the
activity is performed.
To propagate dates upstream click Propagate Date/Quantity, then click Propagate Date
Upstream on the DOP Order or the DOP Orders page.
Prerequisites
This activity requires that the DOP order has components.
System Effects
As a result of this activity:
- The due dates and start dates are updated for the DOP orders at child levels in the DOP structure based on
the due date of the DOP order from which the activity is performed. For information on how this is done, see
Plan DOP Orders.
- If the site has Schedule and Create Load for DOP Order Operations enabled, machine and labor
load of source Scheduled DOP are re-created for the operations on the DOP orders at child levels
in the structure based on the quantity remaining to supply on the DOP orders, plus the planned supply scrap for
that quantity. This applies to the DOP orders with manufactured parts that have the status
Unreleased or Netted and Create Pegged set to Pegged
Orders.