Update DOP Order Date from Supply
Explanation
This activity is used to update the due date of a DOP order to match the latest due date of its pegged supply
orders, provided that at least one pegged supply order exists. As part of this update, the start date will also be
adjusted accordingly.
The due dates of pegged supply orders might change, e.g. due to the usage of constraint based scheduling or
manual re-planning. These updated dates often differ from the dates on the DOP orders. In order to avoid getting
many alarms due to these differences, this activity makes it possible to update the due date of a DOP order based
on the due dates of its pegged supply orders.
To update the due date of a DOP order with the latest due date of its pegged orders, click Update Dates
from Supply and then Order on the DOP Order page or click
Update Dates from Supply on the Alarms tab on the DOP
Order page.
Prerequisites
- This activity requires that the DOP order has at least one pegged supply order.
- To perform the activity from the Alarms tab on the DOP
Order page, a DOP alarm of type Time must exist with the pegged supply order as
the source.
System Effects
As a result of this activity
- The due date of the DOP order is set to the latest due date of its pegged supply orders or, if that date is
not a working day according to the site manufacturing calendar, to the previous workday. The start date is also
updated using backwards planning. For information on how this is done, see Set DOP Order Start Date by Backwards
Planning.
- If the site has Schedule and Create Load for DOP Order Operations enabled, machine and labor
load of source Scheduled DOP are re-created for the DOP order operations based on the quantity
remaining to supply on the DOP order, plus the planned supply scrap for that quantity. This applies if the DOP
order is for a manufactured part and has the status Netted and Create Pegged
set to Pegged Orders.