Correct usage at the last task completion date
This procedure applies to a usage-based recurring task that is not at its first iteration. In this scenario, the ACTV task deadline is incorrect, the task is usage-based, and it has been determined that the task definition is correct and the task is a recurring task. This is not the first time the task has been completed so there is a dependency on the previous task. Since the baseline information is correct, but the current active deadline is incorrect, it means that the last accomplished was not properly recorded. Therefore the information on the historical last accomplished task should be corrected. When this occurs, the deadline of the ACTV task is automatically updated.