Create New Work Package

Explanation

Use this activity to create a new work package in Line Maintenance execution when no suitable package exists for unplanned tasks, unplanned faults, unplanned opportunistic tasks, or follow-on tasks.

You can create the work package in Line Maintenance Execution or in CAMO Line Maintenance Planning.

In Line Maintenance Execution, you can create the work package and put the new item into it in the same action:

In CAMO, the Line/Hangar Planner creates a new work package when no suitable package is available, then assigns unplanned tasks and faults as a separate step. If a suitable work package already exists, assign to that package instead. See Assign Tasks and Faults.

Prerequisites

Procedure

Create a work package when raising a logbook fault

Use this procedure in Line Maintenance Execution when you raise a fault and need a new work package for it. You must be online.

  1. Open the Aircraft Turn Details page and select Raise Fault. The Raise Logbook Fault assistant opens.
  2. Select Raise Logbook Fault. Do not select Raise Non Routine. A non-routine requires an existing work package.
  3. Select Raise and leave open, unless you are recording a historic fault that is already closed. See Raise Fault.
  4. In Fault Registration, turn on Create Work Package.
    • If no work package exists for the turn, a new work package is created and the fault is packaged to it.
    • If a work package already exists for the turn, turn on Create Work Package to create another package and put the fault into it. Leave the option off to assign the fault to an existing work package.
  5. Complete the mandatory fault registration fields: Fault Name, Failed System, Fault Severity, Logbook Reference, Logbook Type, Fault Source, Found On, and Found By. Aircraft and Found During Flight are displayed from the turn when you open the assistant from Aircraft Turn Details.
  6. Complete the mandatory labor requirement fields: Labor Skill and Scheduled Hours (HH:MM). Set Certification Required and Inspection Required if needed.
  7. If required, expand Fault Details and Measurements and complete those fields. See Raise Fault.
  8. Finish the assistant to raise the fault and create the work package.

Note: If you raise a fault from the Line Maintenance Work Package Execution page, the fault is packaged to that work package. Do not use this procedure to create a new work package from that page.

Create a work package when creating an on-condition or ad-hoc task

Use this procedure in Line Maintenance Execution when you create a task and need a new work package for it. The Create Work Package option is available in line maintenance.

  1. Open the Create New Task assistant. From Aircraft Turn Details, the turn status must be Inbound, Arrived, or In Maintenance.
  2. Select Create Task Based on Task Definition to create an on-condition task, or Create Ad-hoc Task to create work without a task definition.
  3. Confirm the Aircraft. The value is pre-filled where possible.
  4. Turn on Create Work Package. The Assigned to Work Package and Assigned to Work Package Name fields are used only when this option is off and you assign the task to an existing work package.
  5. If you selected Create Task Based on Task Definition, select the Config Slot, optionally include task definitions on sub configuration slots, then select an on-condition task definition. See Create Task.
  6. If you selected Create Ad-hoc Task, complete the required task name, configuration slot, labor skill, and scheduled hours. See Create Task.
  7. Select Save or Save & Open to create the task and the work package.

System Effects