View Work Package Commercials

Explanation

You can view the costs, sales, and planning lines of a work package on the Hangar Maintenance Work Package Commercials page.

View Planning Lines

You can view the planning lines of each task on the Planning tab in the Tasks Overview tab. Planning lines denote the planned/scheduled details of the resources.

Planning lines for materials, tools, and personnel are created automatically from the requirements of the task, and you cannot add them manually. You can add planning lines for external costs, expenses, and fixed prices. When the task is in Active, In Work, or Completed status, you can report the external costs and expenses of a planning line using Report Manual Transaction.

The quantity of planning lines is derived as follows:

For materials, tools, and personnel, the planned cost is based on the same unit costs as the cost lines. Customer-owned and supplier-loaned parts have zero cost.

The sales price is fetched from the sales part on the planning line, using the price list or the sales part price. You can change the sales price manually, apply a discount, or enter a markup to calculate the sales price from the cost.

View Cost Lines

Cost lines on the Costs Overview tab and on the Costs tab in the Tasks Overview tab are generated when material is issued, unissued, or returned, when resource time is reported, and when external costs and expenses are reported. Cost lines denote the values actually incurred by the MRO organization.

The unit cost and quantity of cost lines are derived as follows:

View Sales Lines

When a cost line is generated for a task that has a customer, a corresponding sales line is generated automatically. No sales lines are generated for tasks without a customer. Additional sales lines can be created on the Sales tab. Sales lines denote the sales revenue values used to generate the customer invoice.

A generated sales line takes its sales part, sales price, markup, discount, and price list from the planning line, with these exceptions:

For fixed price planning lines, the sales line is created directly from the planning line when the planning line is added to a task manually from the Planning tab in the Tasks Overview. For tasks connected to a contract line with a firm fixed price commercial rule, a fixed price planning line and sales line are created automatically using the fixed price sales part of the rule.

For how sales parts are set on planning lines, see Sales Part Handling in Planning Lines under Prerequisites.

Info: You can use the costing methods below to calculate the selling price:

Finance Transaction Fields

Each cost line includes finance fields that link reported costs to accounting:

You can authorize cost lines from the cost line lists:

On the Tasks Overview tab, select one or more tasks and select Set as Finally Posted to mark the costs of the task as finally posted, or Remove Finally Posted to reverse it. These commands are not available for tasks in Closed status.

From a cost line you can also run Check and Update Accounting when reposting is needed. See Check and Update Accounting of Transaction.

The same finance fields apply on the Line Maintenance Work Package Commercials page. See View Line Maintenance Work Package Commercials for line-specific navigation.

Prerequisites

You need to set up the prerequisites below to view the commercials of a work package and generate the invoice.

Set up Basic Data Requirements for Hangar Maintenance Work Package Commercials

As mandatory basic data requirements for generating costs of the work package, define general costs on the Resource Details page for resources (labor) and tools/equipment, and define costs for materials on the Inventory Part Unit Cost page.

Sales Part Handling in Planning Lines

The sales parts on planning lines are set automatically from the basic data below. If no sales part is found, or to use a different sales part, select one manually on the Planning tab.

Note: The sales part must be active and must belong to the sales site of the task.

Procedure

Follow the steps below to view the planning, sales, and cost lines of a work package.

  1. Navigate to Aviation Maintenance > Hangar Maintenance > Hangar Maintenance Execution > Hangar Maintenance Work Package Commercials.
  2. Select a work package.
  3. View the Total Cost, Total Sales Price Amount/Base, and Total Sales Price Amount/Curr of the work package under the Commercial Summary header.
  4. View the planning, cost, and sales lines of each task on the Planning, Costs, and Sales nested tabs in the Tasks Overview tab.
  5. View the sales and cost lines of the work package on the Sales Overview and Costs Overview tabs.
  6. To view details of the corresponding work package on the Hangar Maintenance Work Package Execution page, click the Work Package Barcode under Work Package Details.

Tip: You can filter the sales and cost lines using the search criteria provided and view the total value of the filtered records.