Specify task dependencies
Make adjustments to a template or production plan by creating dependencies between tasks and other activities.
- Select the task.
Tip: To find a task, you can set a filter, by clicking Set/Reset Filter on the toolbar, or you can press Ctrl+F and type the complete or partial name or barcode of the task.
- Right-click the task and select Edit .
- On the Task Properties dialog box, click the Dependencies tab.
- To create a dependency, do one of the following:
- If the selected task is the dependent in the dependency, click Add in the Previous Activity (From) section.
- If the selected task is the prerequisite in the dependency, click Add in the Following Activity (To) section.
- On the Create Dependency dialog box,
provide the information requested, and click OK:
- Activity: Select whether you want to create a dependency to another task, to a phase, or to a milestone.
- Depending on the choice you made in the
Activity box, the second list box is called
Task, Phase, or
Milestone. In this box, choose the correct activity.
Tip: When creating a dependency to a task, you can enter the full or partial barcode, task name, or external key into the Task box to find matching tasks.
- Dependency: Select one of the following:
- START-START when the prerequisite activity must be started, but not necessarily completed, before the dependent activity can start.
- END-START when the prerequisite activity must be completed before the dependent activity can start.