Lock work packages

Locking work packages prevents them from being rescheduled during automation.
  1. In LRP, do one of the following:
    • To lock a single work package, select it on the Gantt chart.
    • To lock all work packages scheduled to a location, in the Maintenance Line view tab, select the location.
    • To lock all work packages scheduled against an aircraft, in the Aircraft view tab, select the aircraft.
    • To lock all work packages scheduled within the current date range, on the Gantt chart, click, drag, and release to create a selection box around the work packages.
  2. On the toolbar, click Lock Work Package .
  3. In the Lock Work Package dialog box, enter a reason.
  4. Click OK.
    Tip: To unlock a work package, select it on the Gantt chart, and click Unlock Work Package .