Merging work packages (workflow)
You must have control of both block types to merge or add a task to another planner's work package. You must have control of all assigned tasks and blocks to publish or reschedule work packages.
- Planner 2 publishes a plan.
- In the Block Details of the A-check, Planner 2 clears the Read Only check box.
- In the Gantt, Planner 2 double-clicks the work package to be modified.
- On the Work Package Details page, Workscope tab, Planner 2 adds the A-check to the scope of the work package.
- Planner 2 updates the scheduled location of the work package, and clicks OK.
- Planner 2 publishes the plan.
- In the Block Details of the A-check, Planner 2 clears the Read Only check box.
- Planner 1 updates to actuals. Result: The merged work package is loaded into the plan.